Major Milestones

Major Milestones

  • Finishing Touches

    The finishing touches, furniture, storage and seating began on June 10.

  • Exterior Sidewalk Pouring Completed

    The exterior sidewalk was poured on May 8.

  • Epoxy Floor Installation

    The epoxy floor was completed on May 5.

  • Staff Tour

    On April 19, Calgary Academy staff were invited to tour the construction space.

  • Painting complete

    On April 18, interior painting was completed.

  • Masonry Milestone

    On April 11, exterior masonry and brick-laying were completed.

  • Drywall Complete

    On April 4, interior drywall taping and mudding were completed.

  • New Windows Added

    Large south and west-facing windows were installed in the new classroom spaces.

  • Showing the Space to Our Students

    On Mar. 12, our first group of students toured the new space, hosted by Principal Carlson.

  • Touring the Southwest Addition

    On Feb. 29, Board Members and leadership team members toured the space.

  • Concrete Foundation Poured

    On Feb. 15, over 86 cubic metres of concrete foundation was poured.

  • Prepping the Foundation

    In early February, preparation of the foundation began, including the placement of rebar.

  • Roof Installed

    In late January, the steel structure was completed and the roof was installed.

  • Steel Structure

    Steel structural work began in January.

  • Concrete Footings

    On Nov. 21, the foundations of the Southwest Addition began with concrete footing pouring.

  • Excavation Begins

    On Nov. 2, excavation began for construction, including site stripping.

  • Breaking Ground

    On Wednesday, Oct. 18, we officially broke ground on the future site of the southwest addition, marking the first major construction at the school in decades.