Current Construction Updates

 

  • Sept. 3: The Southwest Addition officially opened to staff and students.
  • June 10: The finishing touches of the Southwest Addition began, including furniture and seating arrivals.
  • May 8: The exterior sidewalk was poured.
  • May 5: The Epoxy flooring was completed.
  • April 18: Interior painting was completed.
  • April 11: Extensive work completed over spring break, including interior drywall, HVAC, and boiler work.
  • March 8: Detailed interior work continues, including HVAC and window framing.
  • Feb. 15: Concrete foundation poured–over 86 cubic metres of concrete!
  • Feb. 5: Preparation of the foundation began.
  • Jan 26: Structural steel canopy was complete, installation of the roof underway.
  • Jan 12: Structural steel canopy work continues.
  • Jan. 3: Structural steel canopy work begun.
  • Nov. 21: Concrete footings were poured, and temporary heating equipment has been set up to stave off the cold.
  • Nov. 17: Layout of gridlines complete.
  • Nov. 2: Excavation and site stripping begins.
  • Oct. 23: Construction site fencing and signage in place—project mobilization initiated.
  • Oct. 18: Groundbreaking ceremony with students, staff, and board members.