Major Milestones
-
Open for Learning
The Southwest Addition opened on Sept. 3, 2024, adding 7,500 square feet of new learning spaces, which were completed on time and on budget.
-
Finishing Touches
The finishing touches, furniture, storage and seating began on June 10.
-
Exterior Sidewalk Pouring Completed
The exterior sidewalk was poured on May 8.
-
Epoxy Floor Installation
The epoxy floor was completed on May 5.
-
Staff Tour
On April 19, Calgary Academy staff were invited to tour the construction space.
-
Painting complete
On April 18, interior painting was completed.
-
Masonry Milestone
On April 11, exterior masonry and brick-laying were completed.
-
Drywall Complete
On April 4, interior drywall taping and mudding were completed.
-
New Windows Added
Large south and west-facing windows were installed in the new classroom spaces.
-
Showing the Space to Our Students
On Mar. 12, our first group of students toured the new space, hosted by Principal Carlson.
-
Touring the Southwest Addition
On Feb. 29, Board Members and leadership team members toured the space.
-
Concrete Foundation Poured
On Feb. 15, over 86 cubic metres of concrete foundation was poured.
-
Prepping the Foundation
In early February, preparation of the foundation began, including the placement of rebar.
-
Roof Installed
In late January, the steel structure was completed and the roof was installed.
-
Steel Structure
Steel structural work began in January.
-
Concrete Footings
On Nov. 21, the foundations of the Southwest Addition began with concrete footing pouring.
-
Excavation Begins
On Nov. 2, excavation began for construction, including site stripping.
-
Breaking Ground
On Wednesday, Oct. 18, we officially broke ground on the future site of the southwest addition, marking the first major construction at the school in decades.