Current Construction Updates
- Sept. 3: The Southwest Addition officially opened to staff and students.
- June 10: The finishing touches of the Southwest Addition began, including furniture and seating arrivals.
- May 8: The exterior sidewalk was poured.
- May 5: The Epoxy flooring was completed.
- April 18: Interior painting was completed.
- April 11: Extensive work completed over spring break, including interior drywall, HVAC, and boiler work.
- March 8: Detailed interior work continues, including HVAC and window framing.
- Feb. 15: Concrete foundation poured–over 86 cubic metres of concrete!
- Feb. 5: Preparation of the foundation began.
- Jan 26: Structural steel canopy was complete, installation of the roof underway.
- Jan 12: Structural steel canopy work continues.
- Jan. 3: Structural steel canopy work begun.
- Nov. 21: Concrete footings were poured, and temporary heating equipment has been set up to stave off the cold.
- Nov. 17: Layout of gridlines complete.
- Nov. 2: Excavation and site stripping begins.
- Oct. 23: Construction site fencing and signage in place—project mobilization initiated.
- Oct. 18: Groundbreaking ceremony with students, staff, and board members.