Open for Learning

The Southwest Addition opened on Sept. 3, 2024, adding 7,500 square feet of new learning spaces, which were completed on time and on budget.

Finishing Touches

The finishing touches, furniture, storage and seating began on June 10.

Exterior Sidewalk Pouring Completed

The exterior sidewalk was poured on May 8.

Epoxy Floor Installation

The epoxy floor was completed on May 5.

Staff Tour

On April 19, Calgary Academy staff were invited to tour the construction space.

Painting complete

On April 18, interior painting was completed.

Masonry Milestone

On April 11, exterior masonry and brick-laying were completed.

Drywall Complete

On April 4, interior drywall taping and mudding were completed.

New Windows Added

Large south and west-facing windows were installed in the new classroom spaces.

Showing the Space to Our Students

On Mar. 12, our first group of students toured the new space, hosted by Principal Carlson.